AgentschapNL EVD Internationaal Ministerie van Economische Zaken

NL EVD Internationaal

Sint-Lucia: Additional Financing to the St. Lucia Disaster Management Project II

Datum: 18.07.2008

Uitleg fases

Fase:

Board

Processing Stage:

Active

Abstract:
PID June 10, 2008
Objectives
The objectives of Saint Lucia DMPII are:
(a) to further reduce the country’s vulnerability to
adverse natural events (such as hurricanes, floods etc.) through investing in risk management
activities; and
(b) to strengthen the institutional management and response capacity of the
respective ministries and agencies for disaster management through the provision of facilities,
critical equipment, technical assistance and training.
The proposed AF would support the original objectives of the DMPII and would allow
increasing achievements for the first two outcomes of the project:
(a) percentage of population
with access to improved infrastructure, and
(b) Dennery Village protected from storm surge of a
10 year return.
The project’s outcome and output indicators have been revised and are presented
in Section VI and Annex 4 of the Project Paper.
4.
Description
Proposal for Additional Financing
The proposed AF credit to the Saint Lucia Disaster Management Project II (DMPII) would scale
up investments in Component 1: Physical Prevention and Mitigation Works and would allocate
additional project funds to Component 4: Project Management.
The rationale for the request is:
(i) the need for additional mitigation works to solidify the gains achieved through works
implemented in Dennery Village – one of the most vulnerable communities as prioritized by the
government;
(ii) the continuation of the successful small mitigation works, including small
works in response to last year’s Hurricane Dean, and completion of a technical audit of the small
mitigation works financed under the DMPII; and
(iii) the need to cover some of the additional
project management costs.
The following sections describe the request for this financing in more
detail.
Component 1 - Physical Prevention and Mitigation Works: The estimated cost of these activities
is US$3.345 million (of which US$2.71 million of IDA resources are requested, representing
90% percent of the Additional Financing).
Subcomponent 1
(a): Coastal Protection Dennery Village - Beach Reclamation Efforts: The
estimated cost of these activities is US$360,000 (of which US$306,000 of IDA resources are
requested, representing 10.2% percent of the Additional Financing).
In Dennery, the success of the sea defense construction led to 15,000 square feet of reclaimed
beach, more than originally envisioned – this process was also accelerated by the performance of
the breakwaters during Hurricane Dean.
The additional funds allocated to this sub-component
would support the creation of a communal recreation area, such as a small public park, to prevent
potential encroachment on this land by unauthorized persons, as recommended by the technical
audits.
Three concepts for landscape improvement were proposed to the local community - the
community’s preferred plan depicts landscaping and recreational improvements, providing the
public with an open space for communal use.
Terms of Reference for the final technical designs.
of the public space will be prepared by June 20, 2008.
In the meantime, the PCU will also work
closely with partner agencies to ensure that land encroachment from the newly reclaimed beach
is prevented.
The PCU has hired a Land Surveyor to determine the boundaries of the reclaimed
land.
The survey will be completed by June 30, 2008.
Subcomponent 1
(b): Dennery River and Trou A L’eau Ravine Works: The estimated cost of the
works is US$470,000 (of which US$367,000 of IDA funds are requested, representing 12%
percent of the Additional Financing).
The additional funds allocated to this sub-component would support the revised scope of works,
which entails extension of a berm and elevation of the embankment from the Dennery Bridge;
100 meters upstream to the mouth of the Dennery River, where the existing gabion baskets have
been installed.
This will protect an additional 50 households.
Although not envisioned
originally, work in the area has revealed that this extension is necessary for the newly
constructed river defenses to effectively protect the area against flooding.
An engineering firm
was contracted to conduct a topographical survey that served as the basis for the revised design
of the coastal ravine protection works for the Dennery Village.
An Environmental Assessment
was developed and approved by the Bank in 2004 as part of the original works.
The team’s
environmental and social specialists have checked that the new works proposed, including the
Abbreviated Land Acquisition Plan done under the original project for this purpose, are in
compliance with the Bank’s safeguards policies.
Subcomponent 1
(c): Small Mitigation Works - Integration of Hazard Mapping Objective with
Small Mitigation Works and Technical Audit: The estimated cost for these activities is
US$2,515,000 (of which US$2,037,000 of IDA are requested, representing 68% percent of the
Additional Financing).
The additional funds allocated to this sub-component would support the continuation of
investment in the drainage, river walls and slope stabilization works that is of great interest to the
Government.
In addition, the MCWT&PU would like to conduct a technical audit of the
mitigation works executed under the original project and undertake a scientific analysis of
current landslide vulnerabilities to determine the suitable or appropriate investments.
This
analysis will be used to assess the benefits of the works already completed and to predict slope
stabilities in order to best plan and continue the works.
It will also estimate the potential costs of
landslide and hurricane losses to determine the benefits of local investment in landslide and
hurricane mitigation measures.
The proposal includes obtaining technical assistance from a
specialized NGO who has worked with the Saint Lucian Government on low-cost communitybased
strategies for landslide mitigation.
This component also includes small works for the
recovery from Hurricane Dean last year

Financing Institution:

World Bank

Total Project Cost

USD 3.96 million

Contact:

Ghesquiere, Francis

Agency:

MINISTRY OF ECONOMIC AFFAIRS, ECONOMIC PLANNING, INVESTMENT

More information:

Click here for additional information

 

Bron: World Bank
Nummer: 215367
Trefwoorden: Beveiligingsindustrie - Consultancy - Hulpverlening - Projecten - Saint Lucia - Wereldbank



Meer informatie over dit onderwerp is op te vragen onder vermelding van nummer 215367 bij Mila Bahadoer, e-mail: tio@info.agentschapnl.nl, telefoon: (088) 602 85 87, fax: (088) 602 90 26.